52.242-2
Production Progress Reports. 52.242-2
Effective 10/01/2025 · Subpart 242
Full Text
As prescribed in, insert the following clause: (a) 42.1107
Production Progress Reports (Apr 1991)
(End of clause)
The Contractor shall prepare and submit to the Contracting Officer the production progress reports specified in the contract Schedule. (a)
During any delay in furnishing a production progress report required under this contract, the Contracting Officer may withhold from payment an amount not exceeding $25,000 or 5 percent of the amount of this contract, whichever is less. (b)