Basic. As prescribed in(b) and (b)(1), use the following clause: 234.7101
COST AND SOFTWARE DATA REPORTING SYSTEM—BASIC (NOV 2014)
(a) In the performance of this contract, the Contractor shall use—
(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04–M–1, CSDR Manual;
(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and
(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions (DIDs).
(b) The Contractor shall require CSDR reporting from subcontractors at any tier with a subcontract that exceeds $50 million. If, for subcontracts that exceed $50 million, the Contractor changes subcontractors or makes new subcontract awards, the Contractor shall notify the Government.
(End of clause)
Alternate I. As prescribed in(b) and (b)(2), use the following clause, which uses a different paragraph (b) than the basic clause: 234.7101
COST AND SOFTWARE DATA REPORTING SYSTEM—ALTERNATE I
(NOV 2014)
(a) In the performance of this contract, the Contractor shall use—
(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04–M–1, CSDR Manual;
(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and
(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions (DIDs).
(b) The Contractor shall require CSDR reporting from selected subcontractors identified in the CSDR contract plan as requiring such reporting. If the Contractor changes subcontractors or makes new awards for selected subcontract effort, the Contractor shall notify the Government.
(End of clause)